UMIS Number | BG06RDNP001-19.179-0008-C02 |
Project Name | en |
Beneficiary | 000214552 EN |
Funding | EZFRSR ==> Rural Development Programme |
Date of the Contract/Order | 01.06.2019 |
Start Date | 13.06.2019 |
End Date | 30.06.2019 |
Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
Location of Performance |
|
Brief description |
Кратко описание на проектното предложение (до 2 000 символа) |
Activities |
|
Partners | None |
Contractors |
|
Subcontractors | None |
Members of the Consortium |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Население обхванато от мярката, Measure Unit: %, Base Value: 0.00 , Target amount: 15.00 , Reached amount: 1.00 |
Total Project cost | 51 129.18 EUR |
Grant | 46 016.26 EUR |
Self amount | 5 112.92 EUR |
Total actual amounts paid | -511.29 EUR |
Percentage of EU co-financing | 90.00 % |
|
|||||||||||||||
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: Предмет 05.07.2019,
Estimated Amount: 0.00
|
Procedure 2 |
Subject to due process: Предмет на поръчката,
Estimated Amount: 511 291.88
|
Procedure 3 |
Subject to due process: Предмет на предвидената процедура (до 1 000 символа),
Estimated Amount: 51 129.19
|
Procedure 4 |
Subject to due process: СМР,
Estimated Amount: 2 556.46
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN