Identification

UMIS Number ERBH-1.001-0009-C01
Project Name lom
Beneficiary 176842361 Lom
Funding Other ==> Energy renovation of Bulgarian homes
Date of the Contract/Order 22.02.2018
Start Date 25.01.2017
End Date 09.05.2018
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България, Северозападен, Монтана, Лом, гр.Лом

Description

Brief description
ЕЕ
Activities
  • Activity: То и ОЕЕ: То и ОЕЕ, Contracted Amount: 14 546.66 , Reported Amount: 0.00

Participating Organizations

Partners None
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Отопляема площ, Measure Unit: квадратни метри, Base Value: 3 138.00 , Target amount: 3 138.00 , Reached amount: 0.00
Indicator 2 Общ специфичен разход на енергия (kWh/m2)по потребена енергия - след ЕСМ, Measure Unit: kWh/m2, Base Value: 109.70 , Target amount: 109.70 , Reached amount: 0.00
Indicator 3 Процент на редуцираните енергийни разходи, Measure Unit: kWh/година, Base Value: 73.21 , Target amount: 73.21 , Reached amount: 0.00
Indicator 4 Спестяване на tCO2_Y, Measure Unit: tCO2_Y, Base Value: 126.00 , Target amount: 126.00 , Reached amount: 0.00
Indicator 5 [Нормализирано годишно потребление (Kwh/y)] - по базова линия, Measure Unit: kWh/година, Base Value: 1 284 423.00 , Target amount: 1 284 423.00 , Reached amount: 0.00
Indicator 6 Разгърната застроена площ на сградата, Measure Unit: квадратни метри, Base Value: 3 387.00 , Target amount: 3 387.00 , Reached amount: 0.00
Indicator 7 Спестяване на енергия kWh_Y, Measure Unit: kWh/година, Base Value: 940 406.00 , Target amount: 940 406.00 , Reached amount: 0.00
Indicator 8 Годишн разход на енергия (kWh/y)след ЕСМ, Measure Unit: kWh/y, Base Value: 344 230.00 , Target amount: 344 230.00 , Reached amount: 0.00
Indicator 9 Действително годишно потребление (Kwh/y), Measure Unit: kWh/година, Base Value: 551 236.00 , Target amount: 551 236.00 , Reached amount: 0.00
Indicator 10 Общ специфичен разход на енергия (kWh/m2)по потребена енергия - по базова линия, Measure Unit: kWh/m2, Base Value: 409.30 , Target amount: 409.30 , Reached amount: 0.00

Financial Information

Total Project cost 14 546.66 EUR
Grant 51.13 EUR
Self amount 14 495.53 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 0.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN