UMIS Number | BG-RRP-10.001-0003-C07 |
Project Name | C10.I11 Ensuring an adequate informational and administrative environment for the implementation of the Recovery and Resilience Plan |
Beneficiary | 000695406 Ministry of Finance |
Funding | RRF ==> Recovery and Resilience Plan |
Date of the Contract/Order | 25.07.2022 |
Start Date | 25.07.2022 |
End Date | 31.12.2026 |
Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
Location of Performance |
|
Brief description |
C10.I11 Осигуряване на адекватна информационна и административна среда за изпълнение на Плана за възстановяване и устойчивост |
Activities |
|
Partners |
|
Contractors |
|
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Provision of a repository system for monitoring of the implementation of the RRP_30062023, Measure Unit: Брой, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00 |
Indicator 2 | Update of video guides to cover in full all business processes of the RRP information system, Measure Unit: Брой, Base Value: 0.00 , Target amount: 36.00 , Reached amount: 3.00 |
Indicator 3 | Entry into force of the act setting up the Management and Control system for the RRP, Measure Unit: Брой, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00 |
Indicator 4 | An approved workload analysis for the National Funds Directorate and the Central Coordination Unit, entry into force of the amendments to the structural regulations for the Executive Agency ‘Audit of EU Funds’ and the implementation of respective recommendations, Measure Unit: Брой, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00 |
Indicator 5 | Final recipients trained to strengthen their procurement capacity, including the one of contracting entities, Measure Unit: Брой, Base Value: 0.00 , Target amount: 36.00 , Reached amount: 13.00 |
Indicator 6 | Update of video guides to cover in full all business processes of the RRP information system, Measure Unit: Брой, Base Value: 0.00 , Target amount: 72.00 , Reached amount: 15.00 |
Indicator 7 | Final recipients trained to ensure their capacity to implement the RRP, Measure Unit: Брой, Base Value: 0.00 , Target amount: 800.00 , Reached amount: 80.00 |
Total Project cost | 7 181 253.82 EUR |
Grant | 7 060 080.98 EUR |
Self amount | 121 172.84 EUR |
Total actual amounts paid | 0.00 EUR |
Percentage of EU co-financing | 88.32 % |
|
|||||||||||||||
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: 23,
Estimated Amount: 62.89
|
Procedure 2 |
Subject to due process: Закупуване на 6 бр. санитарни превозни средства за транспорт по въздух (хеликоптери), осигурени с необходимото оборудване и апаратура за нуждите на спешната медицинска помощ по ДБФП № РД-02-37-98/08.10.2020 г. по Проект № BG16RFOP001-4.002-0001, с фин подкрепа на ОП 2014-2020, съфинансирана от ЕС, и Национален план за възстановяване и устойчивост на РБългария, очертаващ помощта от Механизма за възстановяване и устойчивост на Европейския съюз. С реализирането на проекта ще се осигури качествен, равнопоставен и навременен достъп до услугите на Спешната медицинска помощ на гражданите на България и пребиваващи на нейната територия, както и в по-отдалечени и труднодостъпни региони.321321321
,
Estimated Amount: 511 291.88
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN