Identification

UMIS Number BG-RRP-5.002-0001-C02
Project Name Integrating the ecosystem approach and applying nature-based solutions into the protection of Natura 2000 sites
Beneficiary 000697371 Ministry of Environment and Water
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 02.06.2022
Start Date 15.06.2022
End Date 06.04.2023
Status of Implementation of the Contract/Order of the Grant Terminated (termination date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), София-Град (BG411), Столична, гр.София

Description

Brief description
Интегриране на екосистемния подход и прилагане на решения базирани на природата в опазването на защитените зони от мрежата Натура 2000
Activities
  • Activity: първа дейност: 8787, Contracted Amount: 340 009.10 , Reported Amount: 0.00
  • Activity: Втора дейност: 1123321, Contracted Amount: 15 338.76 , Reported Amount: 0.00
  • Activity: Трета дейност: 33, Contracted Amount: 844 142.90 , Reported Amount: 0.00

Participating Organizations

Partners
  • Partner: ban, Contracted Amount*: 15 338.76 , Reported Amount: 0.00
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Development of site-specific conservation objectives and measures for Natura 2000 sites, Measure Unit: Брой, Base Value: 0.00 , Target amount: 2.00 , Reached amount: 0.00
Indicator 2 Restoring climate-related ecosystems through nature-based solutions, Measure Unit: хектари, Base Value: 0.00 , Target amount: 2.00 , Reached amount: 0.00

Financial Information

Total Project cost 84 363.16 EUR
Grant 84 363.16 EUR
Self amount 0.00 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: 123, Estimated Amount: 28 402.26
  • Differentiated position 1: 123123
    Contractor:
    Contract total funded value:

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN