UMIS Number | 2021BG16RFOP001-1.001-0003-C01 |
Project Name | sf |
Beneficiary | 202566561 sv Anna |
Funding | ERDF ==> Programme Health |
Date of the Contract/Order | 18.02.2025 |
Start Date | 05.02.2025 |
End Date | 28.02.2026 |
Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
Location of Performance |
|
Brief description |
Крайбрежните ледници в Антарктика отделят айсберги по-бързо, отколкото природата е в състояние да възстанови леда |
Activities |
|
Partners | None |
Contractors | None |
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | s, Measure Unit: EUR, Base Value: 5.00 , Target amount: 23.00 , Reached amount: 0.00 |
Indicator 2 | en, Measure Unit: Брой, Base Value: 4.00 , Target amount: 22.00 , Reached amount: 0.00 |
Indicator 3 | en, Measure Unit: Брой, Base Value: 4.00 , Target amount: 23.00 , Reached amount: 0.00 |
Indicator 4 | en, Measure Unit: Брой, Base Value: 0.00 , Target amount: 23.00 , Reached amount: 0.00 |
Indicator 5 | dfd, Measure Unit: Брой, Base Value: 3.00 , Target amount: 44.00 , Reached amount: 0.00 |
Total Project cost | 14 148.45 EUR |
Grant | 8 461.77 EUR |
Self amount | 5 686.68 EUR |
Total actual amounts paid | 0.00 EUR |
Percentage of EU co-financing | 20.00 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: оставка, монтиране и въвеждане в експлоатация на 7 броя обзаведени контейнери - представляващи помещения за хранене, събличане, спорт и активна почивка за работниците и служителите на "фф" ЕООД,
Estimated Amount: 4 090 335.05
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN