UMIS Number | 2021BG16FFPR002-1.001-0001-C02 |
Project Name | Second phase of project - Water supply and sewerage TEST |
Beneficiary | Вики |
Funding | CF ==> Programme "Environment" 2021-2027 |
Date of the Contract/Order | 29.08.2023 |
Start Date | 29.08.2023 |
End Date | 24.07.2025 |
Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
Location of Performance |
|
Brief description |
тест |
Activities |
|
Partners | None |
Contractors | None |
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Population connected to improved public water supply, Measure Unit: лица, Base Value: 0.00 , Target amount: 100.00 , Reached amount: 0.00 |
Total Project cost | 511.29 EUR |
Grant | 460.16 EUR |
Self amount | 51.13 EUR |
Total actual amounts paid | 1 023.10 EUR |
Percentage of EU co-financing | 85.00 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
There are no tender procedures |
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN